Yau Tong Public Housing Construction in the third quarter of next year

The Housing Authority submitted a document to the Legislative Council showing that it is proposed to apply for a provision of $111.8 million for the public housing project at Yau Wing Street, Yau Tong, for the purpose of flattening and sewage disposal works. It is expected to commence in the third quarter of next year and be completed in the first quarter of 2021. .

According to the data, the project consists of two public housing units, which are expected to provide about 2,000 people. It is expected to be constructed in the third quarter of next year and completed in 2024/25.